11 Development Charges & Appeal · 11.1 Development charges
11.1.5 Development charge numericals: land, building, combined use, interest and penalty
Development charge sums need only three things — the area, the ASR rate of developed land per sq m, and the Second Schedule percentage (0.5% land, 2% building, ×1.5 industrial, ×2 commercial) — and interest, refund and penalty questions use 12% simple interest (18% before Mah. 44 of 2025) and the s.124K fine limits.
- MPSC ATP
- Standard level
- 7 min read
- Full course
Key terms
- development charge calculation
- ASR rate
- ready reckoner
- 0.5 per cent
- 2 per cent
- industrial 1.5 times
- commercial 2 times
- combined land and building
- Vital Urban Transport Project
- 12 per cent interest
- 18 per cent before 2025
- section 124I refund
- section 124K fine
- Heritage Conservation Fund
What this note covers
- Core factsFoundation
- ExplainedStandard
- DeeperAdvanced
- Mains writingMains writing
- Common trapsFoundation
- Quick revisionFoundation
Read the full note in the app. It is part of the MPSC ATP full course in Medha AI. Free in the app: the first note of each topic.
All Development charges notes · MPSC ATP syllabus · MPSC ATP Mock Test 1 with answers · Start free
Medha AI writes its own notes and checks them against the sources listed. Medha AI is an independent preparation service. It is not affiliated with, endorsed by or connected to APPSC, TSPSC, MPSC, UPSC or any other commission or government body.