A town planning scheme (TPS) pools the irregular plots of an area, takes out land for roads and amenities, and returns reshaped "final plots" to the owners, paying for the works out of a share of the rise in land value; in Maharashtra it is made under Chapter V (ss.59–112) of the MRTP Act, 1966.
- MPSC ATP
- Standard level
- 8 min read
- Free
Core facts
- Law: MRTP Act, 1966, Chapter V "Town Planning Schemes", ss.59–112.
- First law in the State to allow TP schemes: the Bombay Town Planning Act, 1915. Then the Bombay Town Planning Act, 1954, then the MRTP Act, 1966.
- Who makes it: the Planning Authority (s.59). The State Government can direct it to make one (s.63).
- Purpose: to implement the proposals of the final Development Plan in detail, or for land likely to be in the course of development or already built upon (s.59(1)(a); the second limb added by Mah. 35 of 2014).
- Technique: land readjustment / land pooling. Land is not wholly acquired. Owners get back a smaller but serviced, regular plot.
- Key terms:
- Original plot (OP): the plot as it stood before the scheme.
- Final plot (FP): the plot allotted after reconstitution (s.65).
- Increment: the rise in value due to the scheme (s.98).
- Contribution: the levy on each FP, not more than half the increment (s.99).
- Quasi-judicial officer: the Arbitrator (s.72). Appeals on valuation matters go to the Tribunal of Appeal (President + two Assessors, s.75).
- Joint scheme (s.96): for contiguous areas of two or more Planning Authorities, the State constitutes a Special Planning Authority (as in s.40).
Explained
Why a TPS instead of acquisition
- Owners stay on their land. Only a part is taken for roads, open spaces and amenities.
- The cost is recovered from the owners who benefit (betterment), not from the general budget.
- Owners whose plots shrink are credited for the land lost; this is set off against the contribution (s.100).
Stages under the current (amended) Act
| Stage | Section | Who |
|---|---|---|
| Declaration of intention (by resolution) | s.60 | Planning Authority |
| Town Planning Officer appointed at declaration | s.60A (2025) | Planning Authority |
| Draft scheme made; notice published; objections | ss.61, 67 | Planning Authority |
| Draft scheme sanctioned | s.68 | State Government |
| Arbitrator appointed | s.72(1) | State Government |
| Preliminary scheme, then final scheme | s.72 | Arbitrator |
| Appeals on valuation matters | ss.74–82 | Tribunal of Appeal |
| Preliminary and final schemes sanctioned (deemed sanctioned if not decided in time, 2025) | s.86 | State Government |
- The 1966 text (to 2011) had only one post-draft stage, the final scheme drawn up by the Arbitrator. Mah. 35 of 2014 (w.e.f. 24-12-2014) split it into a preliminary scheme (physical layout: roads, reservations, final plots, allottees) and a final scheme (money: values, increment, contribution, compensation).
- When the preliminary scheme comes into force, land needed by the Planning Authority vests in it (s.88). Land for roads, drainage, street lighting and water supply vests even earlier, in the Appropriate Authority, on sanction of the draft scheme (s.68A).
Physical part and financial part
- Physical planning: road network, reservations, reconstitution of plots (s.65).
- Valuation: original value, semi-final value, final value, increment, contribution, net demand (ss.97–100).
- A draft scheme therefore contains both physical proposals and valuation particulars (s.64).
Joint town planning schemes (s.96)
- The State Government, or two or more Planning Authorities, may decide that contiguous areas are best served by a joint DP or joint TPS.
- The State Government, after inquiry, constitutes a Special Planning Authority as provided in s.40.
- That authority declares its intention as under s.23 (for a DP) or s.60 (for a TPS) and has all the powers of a Planning Authority.
- On sanction (s.31 for a DP; s.86 for a TPS), each part works in its area as if it were a separate plan or scheme. The authorities may also execute it jointly.
TPS and UDCPR
- UDCPR applies in TPS areas too, but permission can still be given wholly under the scheme's own regulations (Reg. 1.1(ii)).
- In the agricultural zone, UDCPR allows a TPS under Chapter V for a minimum 20 ha, with a proper road network and the entire cost borne by the owners. After the preliminary scheme is sanctioned under s.86, residential-zone uses and FSI apply.
- As an alternative, owners may pool land themselves on the same concept: a 12 m approach road and 40% of the land earmarked for roads, parks, social infrastructure and sale by the Authority (at least 10% parks and playgrounds, 15% social infrastructure and sale, roads counted up to 15%).
Common traps
- ✗ "TP schemes are in Chapter III of the MRTP Act." ✓ Chapter V (ss.59–112). Chapter III is the Development Plan.
- ✗ "The first Act to allow TP schemes in Maharashtra was the 1954 Act." ✓ The Bombay Town Planning Act, 1915.
- ✗ "A TPS is a land acquisition technique." ✓ It is land pooling / readjustment; owners get final plots back.
- ✗ "For a joint scheme, each Planning Authority makes its own scheme." ✓ The State constitutes a Special Planning Authority (s.96, as in s.40).
- ✗ "TDR is a land assembly technique." ✓ TDR is a compensation tool, not land assembly.
- ✗ "UDCPR does not apply in TPS areas." ✓ It applies (Reg. 1.1(ii)), but permission may be given wholly under the TPS regulations.
Quick revision
- TPS: Chapter V, ss.59–112, MRTP Act 1966.
- First TPS law: Bombay TP Act 1915; then 1954; then MRTP 1966.
- Made by the Planning Authority to implement the final DP, or for developing/built-up land (s.59).
- OP → reconstitution (s.65) → FP.
- Increment (s.98); contribution ≤ half increment (s.99).
- Arbitrator (s.72); Tribunal of Appeal: President + 2 Assessors (s.75).
- Stages: declaration (+ TPO, s.60A) → draft → sanction → Arbitrator → preliminary → final → sanction (s.86).
- Joint TPS: Special Planning Authority (s.96 with s.40).
- UDCPR agri-zone TPS: minimum 20 ha, cost borne by owners.
Go deeper: Deeper, Mains writing (beyond what MPSC ATP usually asks)
Deeper Advanced
- Land readjustment as a family. The TPS belongs to the same family as Japan's land readjustment (kukaku seiri) and Germany's Umlegung. The common rule: the public share of land and cost comes from the owners in proportion to the gain they receive.
- Land assembly techniques in Indian practice: TP schemes, land pooling (e.g. Amaravati, Delhi's land pooling policy), plot reconstitution and guided development. TDR is not a land assembly technique; it is a form of compensation.
- Why the later overhaul. Under the 1966 text a scheme often took a decade or more because land vested only when the whole final scheme, with all valuation disputes, was sanctioned. Splitting the stages lets roads and plots be delivered on the preliminary scheme, while money disputes go on separately.
- Gujarat's model. Gujarat's Act of 1976 used a preliminary/final split and later added fixed land shares; Maharashtra's later amendments moved closer to it (see UPL-TS-11).
- A TPS is "law". On the date fixed in the s.86 notification, the scheme "shall have effect as if it were enacted in this Act" (s.86(3)). So its provisions bind everyone, including the Planning Authority.
Mains writing Mains writing
- Frame: the TPS is a self-financing, owner-inclusive way to convert raw land into serviced urban land without mass acquisition.
- Analysis points:
- Equity: owners keep land and share in the gain; the public gets roads and amenities.
- Finance: the contribution (betterment) and the sale plots fund the works.
- Weaknesses: long timelines, valuation disputes, weak execution of works after sanction.
- Way forward: time-bound stages, GIS-based plot records, early vesting of road land, and sale plots to fund trunk infrastructure.
- Example: Pune and Ahmedabad have used TPSs to open up peri-urban land with planned road grids.
Practise this topic. Questions on Town Planning Scheme, with answers explained.
All Town planning schemes notes · MPSC ATP syllabus · MPSC ATP Mock Test 1 with answers · Start free
Medha AI writes its own notes and checks them against the sources listed. Medha AI is an independent preparation service. It is not affiliated with, endorsed by or connected to APPSC, TSPSC, MPSC, UPSC or any other commission or government body.