15 Land Acquisition · 15.4 RFCTLARR Act 2013: urgency, Authority and miscellaneous
15.4.1 RFCTLARR Section 40: urgency acquisition and its extra compensation
Section 40 lets the Collector take possession before the award — 30 days after the s.21 notice — but only for the minimum area needed for defence, national security or natural-calamity emergencies, after tendering 80% of the estimated compensation, and the owner then gets an extra 75% of the compensation.
- MPSC ATP
- Standard level
- 7 min read
- Full course
Key terms
- urgency clause
- section 40
- defence of India
- national security
- natural calamities
- approval of Parliament
- thirty days after section 21 notice
- forty-eight hours notice
- 80 per cent tender
- 75 per cent additional compensation
- section 9 SIA exemption
- section 17 of 1894 Act
What this note covers
- Core factsFoundation
- ExplainedStandard
- DeeperAdvanced
- Mains writingMains writing
- Common trapsFoundation
- Quick revisionFoundation
Read the full note in the app. It is part of the MPSC ATP full course in Medha AI. Free in the app: the first note of each topic.
All RFCTLARR Act 2013: urgency, Authority and miscellaneous notes · MPSC ATP syllabus · MPSC ATP Mock Test 1 with answers · Start free
Medha AI writes its own notes and checks them against the sources listed. Medha AI is an independent preparation service. It is not affiliated with, endorsed by or connected to APPSC, TSPSC, MPSC, UPSC or any other commission or government body.